Project details
- Customer: ATUBO (Walo – PORR – Specogna)
- Building owner: Canton of Bern
- Construction time RSB: August 2010 – August 2011
- Dimensions:
Formwork length: 12,50 m
Sformwork weight: 165 t - Special features:
The RSB machine was designed to be able to concrete the emergency stops as well as to be transported through the exit tunnel without major dismantling work.