Chinegga Bridge Road Bypass

Stalden

Switzerland

Special constructions Formwork systems

Project details

  • Customer: Ulrich Imboden AG. Hoch- und Tiefbau
  • Building owner: Canton Valais, Dep. for Transport, Construction and Environment
  • Construction time RSB: April 2018 – May 2018
  • Abmessungen:
    Height: 70 m
    Diameter: from 3.3 m to 2.2 m
    Gradient: 100:1

  • Special features:
    2 bridge piers will be constructed in exposed concrete quality. RSB has 2 working platforms in use, which is why every day one 4.4 m pier section is concreted in turn while the other is reinforced.
Chinegga bridge, Stalden bypass - Switzerland

Contact us

Data privacy / DSGVO

3 + 11 =

RSB Formwork Technology

Schilfweg 1 · 6972 Fußach · Austria

n

+43 (0) 5578 7960-400

Subscribe to newsletter