Working platform smoke extraction shaft Kramertunnel Garmisch Partenkirchen Germany

Special constructions Formwork systems

Project details

  • Customer: ARGE Kramertunnel, BeMo Tunneling – Subterra
  • Building owner: Federal Republic of Germany
  • Construction time RSB: May 2022
  • Volume:
  • Dimensions:
  • Besonderheiten: For the 85m deep and 5.5m large ventilation shaft at the Kramertunnel in Garmisch-Partenkirchen, our multiple-purpose-platform is used to carry out inspection and installation work.
    The platform was anchored at different heights in the shaft wall.
For the 85m deep and 5.5m large ventilation shaft at the Kramertunnel in Garmisch-Partenkirchen, our multiple-purpose-platform is used to carry out inspection and installation work.

Contact us

Hinweise zur Verarbeitung Ihrer Angaben

15 + 1 =

RSB Formwork Technology

Schilfweg 1 · 6972 Fußach · Austria

n

+43 (0) 5578 7960-400

Subscribe to newsletter