1.
Uplift protection to tie the funnel-shaped formwork

2.
Reinforcement work, installation of inserts


3.
Reinforcement complete - uplift protection plate assembled


4.
Assembly of the funnel-shaped formwork (supporting steel skeleton)


5.
Funnel-shaped formwork assembled, ready for concrete work




6.
Continuous concrete work, optimum compacting, maximum concrete drop 50 cm


7.
Disassembly of funnel-shaped formwork

8.
Funnel after stripping of formwork